Adjustments to Domestic Production in January and in February

(Updated on January 25, 2022 from the announcement on January 24, 2022)

Due to the shortage of parts supply caused by the spread of COVID-19 at our supplier in Japan, on January 21 we announced additional suspensions of domestic plant production for completed vehicles () and also our revised production plan for February () due to the shortage of semiconductor-related parts.

Today, Toyota announces additional suspensions of domestic plant production for completed vehicles.

With regard to February, as the parts scheduled to be used during the January suspension can now be used in February, some plants and lines originally scheduled to be suspended in the month will now operate. We will continue to make our maximum efforts to deliver as many vehicles as possible to our customers at the earliest possible date.

We sincerely apologize for the inconvenience this may cause to our customers and suppliers due to these changes.

Production suspension after January 25 (Tue) (19 lines in 11 plants out of 28 lines in 14 plants)

PlantsPeriod of production suspensionProduction vehicle
Toyota Motor Corporation

Motomachi Plant

Production line #125 (Tue), 26 (Wed), 27 (Thu), 28 (Fri), 31 (Mon)Crown, Noah, Voxy, Mirai
Production line for GR modelsGR Yaris
Production line for low volume modelsLC
Toyota Motor Corporation

Takaoka Plant

Production line #1Corolla, Corolla Touring, Corolla Cross
Toyota Motor Corporation

Tsutsumi Plant

Production line #1Prius, Prius PHV, Corolla
Production line #2Corolla Sport, Camry, ES
Toyota Motor Corporation

Tahara Plant

Production line #1Land Cruiser Prado, GX, 4Runner
Production line #3LS, IS, RC, RC F, NX
Toyota Motor East Japan

Iwate Plant

Production line #1C-HR, Aqua
Production line #2Yaris, Yaris Cross, Aqua
Toyota Motor East Japan

Miyagi Ohira Plant

Yaris Cross, Sienta, Corolla Axio, Corolla Fielder, JPN Taxi
Toyota Auto Body

Fujimatsu Plant

Production line #1Land Cruiser 70
Production line #2Noah, Voxy
Toyota Auto Body

Inabe Plant

Production line #1Hiace, Granace, Alphard, Vellfire, LM
Toyota Auto Body

Yoshiwara Plant

Production line #1LX, Land Cruiser 300
Production line #2Land Cruiser 70
Gifu Auto BodyProduction line #1Hiace / Ambulance, Granace
Production line #2Coaster
Hino Motors, Ltd.

Hamura Plant

Production line #1Land Cruiser Prado, FJ Cruiser

Production suspension in February (7 lines in 6 plants (previously announced as 11 lines in 8 plants) out of 28 lines in 14 plants)

The strike-through lines have been changed to “Operation”.
PlantsPeriod of production suspensionProduction vehicles
Toyota Motor Corporation

Motomachi Plant

GR line1 (Tue), 2 (Wed), 3 (Thu), 4 (Fri), 7 (Mon), 8 (Tue), 9 (Wed), 10 (Thu), 11 (Fri), 14 (Mon), 15 (Tue), 16 (Wed)GR Yaris
Toyota Motor Corporation

Takaoka Plant

Production line #112 (Sat), 19 (Sat)Corolla, Corolla Touring, Corolla Cross
Production line #212 (Sat), 19 (Sat)RAV4, Harrier
Toyota Motor Corporation

Tsutsumi Plant

Production line #112 (Sat), 19 (Sat)Prius, Prius PHV, Corolla
Production line #212 (Sat), 19 (Sat)Corolla Sport, Camry, ES
Toyota Motor Corporation

Tahara Plant

Production line #34 (Fri), 11 (Fri), 12 (Sat), 19 (Sat)LS, IS, RC, RC F, NX
Toyota Motor Kyushu

Miyata Plant

Production line #12 (Wed), 3 (Thu), 4 (Fri), 9 (Wed), 10 (Thu), 11 (Fri), 12 (Sat), 17 (Thu), 18 (Fri), 19 (Sat)NX, NX PHV, CT, UX, UX300e
Toyota Motor East Japan

Iwate Plant

Production line #11 (Tue), 2 (Wed), 3 (Thu), 4 (Fri), 7 (Mon), 8 (Tue), 9 (Wed), 10 (Thu), 11 (Fri), 12 (Sat), 14 (Mon)C-HR, Aqua
Production line #2Yaris, Yaris Cross, Aqua
Toyota Motor East Japan

Miyagi Ohira Plant

1 (Tue), 2 (Wed), 3 (Thu), 4 (Fri), 12 (Sat)Yaris Cross, Sienta, Corolla Axio, Corolla Fielder, JPN Taxi
Toyota Auto Body

Fujimatsu Plant

Production line #21 (Tue), 2 (Wed), 3 (Thu), 4 (Fri), 7 (Mon), 8 (Tue), 9 (Wed), 10 (Thu), 11 (Fri), 12 (Sat), 14 (Mon), 15 (Tue), 16 (Wed)Noah, Voxy

/Public Release. View in full .