We at Toyota would like to again apologize for the repeated adjustments to our production plans due to the parts shortage resulting from the spread of COVID-19, and for causing considerable inconvenience to our customers who have been waiting for the delivery of vehicles, suppliers, and other parties concerned.
We have decided to suspend operations at some of our domestic plants from June 17 (Friday) due to low attendance caused by a COVID-19 outbreak at one of our suppliers, and a shortage of parts supply caused by a production equipment defect at another supplier. The suspension plan this time is in addition to the recent announcement ().
As a result of those suspensions, the number of units affected will be approximately 40,000 and the global production plan for June is revised to be approximately 750,000 units from the original plan (approx. 800,000 units). The production forecast for the fiscal year remains unchanged (approx. 9.7 million).
The global production plan for July will be announced at a later date.
As it remains difficult to look ahead due to the shortage of semiconductors and the spread of COVID-19, there is a possibility that the production plan may be lower. However, we will examine the parts supply closely to minimize sudden decreases in production, and continue to make every effort possible to deliver as many vehicles to our customers at the earliest date.
The following is the suspension schedule of domestic operations in June and July.
Suspension of production in June and July (11 lines in 7 plants out of 28 lines in 14 plants)
Plants | Period of production suspension (Announced on May 27) | Period of production suspension | Production vehicle | |
---|---|---|---|---|
Toyota Motor Corporation Motomachi Plant | Production line #1 | June 6 (Mon), 7 (Tue), 8 (Wed), 9 (Thu), 10 (Fri) | June 17 (Fri)*1, 20 (Mon), 21 (Tue), 22 (Wed), 23 (Thu), 24 (Fri), 27 (Mon), 28 (Tue), 29 (Wed), 30 (Thu), July 1 (Fri) | Crown, Noah, Voxy, MIRAI, bZ4X |
Production line for GR models | GR Yaris | |||
Production line for low volume models | June 20 (Mon), 21 (Tue), 22 (Wed), 23 (Thu), 24 (Fri), 27 (Mon), 28 (Tue), 29 (Wed), 30 (Thu), July 1 (Fri) | LC | ||
Toyota Motor Corporation Takaoka Plant | Production line #1 | June 2 (Thu), 3 (Fri), 6 (Mon), 7 (Tue), 8 (Wed), 9 (Thu), 10 (Fri) | ― | Corolla, Corolla Cross, Corolla Touring |
Production line #2 | June 6 (Mon), 7 (Tue), 8 (Wed), 9 (Thu), 10 (Fri) | June 27 (Mon), 28 (Tue), 29 (Wed), 30 (Thu), July 1 (Fri), 4 (Mon), 5 (Tue), 6 (Wed), 7 (Thu), 8 (Fri) | RAV4, Harrier | |
Toyota Motor Corporation Tsutsumi Plant | Production line #1 | ― | Prius, Prius PHV, Corolla | |
Toyota Motor Corporation Tahara Plant | Production line #1 | Land Cruiser Prado, GX, 4Runner | ||
Production line #3 | June 27 (Mon), 28 (Tue), 29 (Wed), 30 (Thu), July 1 (Fri) | LS, IS, RC, RC F, NX | ||
Toyota Motor Kyushu Miyata Plant | Production line #1 | June 2 (Thu), 3 (Fri), 6 (Mon), 7 (Tue), 8 (Wed), 9 (Thu), 10 (Fri) | ― | NX, NX450h+, CT, UX, UX300e |
Production line #2 | ES, RX | |||
Toyota Motor East Japan Iwate Plant | Production line #1 | June 1 (Wed), 2 (Thu), 3 (Fri), 6 (Mon), 7 (Tue), 8 (Wed), 9 (Thu), 10 (Fri) | June 27 (Mon), 28 (Tue), 29 (Wed), 30 (Thu), July 1 (Fri) | Aqua, C-HR |
Production line #2 | ― | Aqua, Yaris, Yaris Cross | ||
Toyota Motor East Japan Miyagi Ohira Plant | June 1 (Wed), 2 (Thu), 3 (Fri), 6 (Mon), 7 (Tue), 8 (Wed), 9 (Thu), 10 (Fri) | Yaris Cross, Sienta, Corolla Axio, Corolla Fielder, JPN Taxi | ||
Toyota Auto Body Fujimatsu Plant | Production line #2 | ― | Noah, Voxy | |
Toyota Auto Body Inabe Plant | Production line #1 | June 6 (Mon), 7 (Tue), 8 (Wed), 9 (Thu), 10 (Fri) | ― | Hiace, Granace, Alphard, Vellfire, LM |
Toyota Auto Body Yoshiwara Plant | Production line #1 | June 27 (Mon), 28 (Tue), 29 (Wed), 30 (Thu), July 1 (Fri) | LX, Land Cruiser 300 | |
Production line #2 | Land Cruiser 70 | |||
Daihatsu Motor Corporation Kyoto (Oyamazaki) Plant*2 | June 1 (Wed), 2 (Thu), 3 (Fri), 6 (Mon), 7 (Tue), 8 (Wed), 9 (Thu), 10 (Fri) | ― | Probox |
*1 | Production suspension for the second shift only |
---|---|
*2 | Daihatsu Kyoto (Oyamazaki) single shift operation |