Adjustments to Domestic Production in May

We at Toyota would like to once again apologize for the repeated adjustments to our production plans due to the parts shortage resulting from the spread of COVID-19, which has caused considerable inconvenience to our customers, suppliers and other parties concerned.

Due to the impact of the semiconductor shortage, we announced our revised production plan for May (). However, as a result of the lockdown in Shanghai, China, we have decided to additionally suspend operations of 14 lines at 8 plants in Japan from May 16 (Mon) to May 21 (Sat). (Please see following chart for details)

We had announced that our global production plan for May would be approximately 750,000 units, but due to the impact of the lockdown, it is expected to be around 700,000 units.

The shortage of semiconductors, spread of COVID-19 and other factors are making it difficult to look several months ahead. Still, we will continue to make maximum efforts to deliver as many vehicles as possible to our customers at the earliest possible date.

The following is the suspension schedule of domestic operations in May due to plan revisions.

Production suspension in May (20 lines at 12 plants of the total 28 lines at 14 plants)

PlantsPeriod of production suspension

(Announced on April 18)

Period of production suspension

(Announced on May 10)

Production vehicles
Toyota Motor Corporation

Motomachi Plant

Production line #1May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri)Crown, Noah, Voxy, MIRAI, bZ4X
Production line for GR modelsGR Yaris
Production line for low volume modelsLC
Production line for CenturyCentury
Toyota Motor Corporation

Takaoka Plant

Production line #1May 9 (Mon), 20 (Fri)Corolla, Corolla Cross, Corolla Touring
Production line #2May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri)Harrier, RAV4
Toyota Motor Corporation

Tsutsumi Plant

Production line #1May 9 (Mon), 20 (Fri)Prius, Prius PHEV, Corolla
Toyota Motor Corporation

Tahara Plant

Production line #1May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri)Land Cruiser Prado, GX, 4Runner
Production line #3May 12 (Thu)May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri)LS, IS, RC, RC F, NX
Toyota Motor Kyushu

Miyata Plant

Production line #1May 9 (Mon), 10 (Tue), 13 (Fri), 16 (Mon), 20 (Fri), 23 (Mon)May 17 (Tue), 18 (Wed), 19 (Thu)NX, NX PHEV, CT, UX, UX BEV
Production line #2May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri)ES, RX
Toyota Motor East Japan

Iwate Plant

Production line #1May 9 (Mon), 10 (Tue), 11 (Wed)C-HR, Aqua
Toyota Auto Body

Fujimatsu Plant

Production line #2May 9 (Mon), 10 (Tue), 11 (Wed), 12 (Thu), 13 (Fri), 16 (Mon)Noah, Voxy
Toyota Auto Body

Inabe Plant

Production line #1May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri)Hiace, Granace, Alphard, Vellfire, LM
Toyota Auto Body

Yoshiwara Plant

Production line #1May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri), 21 (Sat)*1LX, Land Cruiser 300
Production line #2Land Cruiser 70
Gifu Auto BodyProduction line #2May 9 (Mon), 10 (Tue), 11 (Wed), 12 (Thu)May 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri)Coaster
Toyota Industries CorporationProduction line #301May 21 (Sat), 28 (Sat)*1RAV4
Production line #302May 16 (Mon), 17 (Tue)RAV4, RAV4 PHEV
Daihatsu Motor Corporation

Kyoto (Oyamazaki) Plant*2

May 18 (Wed), 19 (Thu)Probox
*1Single shift operation on Saturdays
*2Single shift operation at the Daihatsu Kyoto (Oyamazaki) Plant

/Public Release. View in full .