We at Toyota would like to once again apologize for the repeated adjustments to our production plans due to the parts shortage resulting from the spread of COVID-19, which has caused considerable inconvenience to our customers, suppliers and other parties concerned.
Due to the impact of the semiconductor shortage, we announced our revised production plan for May (). However, as a result of the lockdown in Shanghai, China, we have decided to additionally suspend operations of 14 lines at 8 plants in Japan from May 16 (Mon) to May 21 (Sat). (Please see following chart for details)
We had announced that our global production plan for May would be approximately 750,000 units, but due to the impact of the lockdown, it is expected to be around 700,000 units.
The shortage of semiconductors, spread of COVID-19 and other factors are making it difficult to look several months ahead. Still, we will continue to make maximum efforts to deliver as many vehicles as possible to our customers at the earliest possible date.
The following is the suspension schedule of domestic operations in May due to plan revisions.
Production suspension in May (20 lines at 12 plants of the total 28 lines at 14 plants)
Plants | Period of production suspension (Announced on April 18) | Period of production suspension (Announced on May 10) | Production vehicles | |
---|---|---|---|---|
Toyota Motor Corporation Motomachi Plant | Production line #1 | ― | May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) | Crown, Noah, Voxy, MIRAI, bZ4X |
Production line for GR models | ― | GR Yaris | ||
Production line for low volume models | ― | LC | ||
Production line for Century | ― | Century | ||
Toyota Motor Corporation Takaoka Plant | Production line #1 | May 9 (Mon), 20 (Fri) | ― | Corolla, Corolla Cross, Corolla Touring |
Production line #2 | ― | May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) | Harrier, RAV4 | |
Toyota Motor Corporation Tsutsumi Plant | Production line #1 | May 9 (Mon), 20 (Fri) | ― | Prius, Prius PHEV, Corolla |
Toyota Motor Corporation Tahara Plant | Production line #1 | ― | May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) | Land Cruiser Prado, GX, 4Runner |
Production line #3 | May 12 (Thu) | May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) | LS, IS, RC, RC F, NX | |
Toyota Motor Kyushu Miyata Plant | Production line #1 | May 9 (Mon), 10 (Tue), 13 (Fri), 16 (Mon), 20 (Fri), 23 (Mon) | May 17 (Tue), 18 (Wed), 19 (Thu) | NX, NX PHEV, CT, UX, UX BEV |
Production line #2 | ― | May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) | ES, RX | |
Toyota Motor East Japan Iwate Plant | Production line #1 | May 9 (Mon), 10 (Tue), 11 (Wed) | ― | C-HR, Aqua |
Toyota Auto Body Fujimatsu Plant | Production line #2 | May 9 (Mon), 10 (Tue), 11 (Wed), 12 (Thu), 13 (Fri), 16 (Mon) | ― | Noah, Voxy |
Toyota Auto Body Inabe Plant | Production line #1 | ― | May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) | Hiace, Granace, Alphard, Vellfire, LM |
Toyota Auto Body Yoshiwara Plant | Production line #1 | ― | May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri), 21 (Sat)*1 | LX, Land Cruiser 300 |
Production line #2 | Land Cruiser 70 | |||
Gifu Auto Body | Production line #2 | May 9 (Mon), 10 (Tue), 11 (Wed), 12 (Thu) | May 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) | Coaster |
Toyota Industries Corporation | Production line #301 | May 21 (Sat), 28 (Sat)*1 | ― | RAV4 |
Production line #302 | May 16 (Mon), 17 (Tue) | RAV4, RAV4 PHEV | ||
Daihatsu Motor Corporation Kyoto (Oyamazaki) Plant*2 | May 18 (Wed), 19 (Thu) | ― | Probox |
*1 | Single shift operation on Saturdays |
---|---|
*2 | Single shift operation at the Daihatsu Kyoto (Oyamazaki) Plant |