We at Toyota would like to again apologize for the repeated adjustments to our production plan due to the parts shortage resulting from the spread of COVID-19, and for causing considerable inconvenience to our customers, who have been waiting for the delivery of vehicles, suppliers, and other parties concerned.
Due to the impact of the semiconductor shortage, we announced adjustments to domestic production in October (““). However, we have decided to make additional suspensions of operations at some plants and lines in Japan. The global production volume affected by this decision is approximately 50,000 units (including 25,000 units in Japan), and although we announced global production plan for October was approximately 800,000 units, it is expected to be around 750,000 units by this decision.
The production forecast for the fiscal year remains unchanged at approx. 9.7 million.
The following is the revised domestic operations suspension schedule for October.
Suspension of production in October (5 lines in 5 plants out of 28 lines in 14 plants)
Plant | Period of production suspension (Announced on September 22) | Period of production suspension (Announced this time) | Production model | |
---|---|---|---|---|
Toyota Motor Corporation Motomachi Plant | Production line for GR models | October 3 (Mon), 4 (Tue) | ― | GR Yaris |
Toyota Motor Corporation Takaoka Plant | Production line #2 | October 7 (Fri), 8 (Sat), 10 (Mon), 11 (Tue), 12 (Wed), 13 (Thu), 14 (Fri), 15 (Sat), 17 (Mon), 18 (Tue), 19 (Wed), 20 (Thu) | RAV4, Harrier | |
Toyota Motor Corporation Tsutsumi Plant | Production line #1 | ― | October 8 (Sat), 10 (Mon), 11 (Tue), 12 (Wed), 13 (Thu), 14 (Fri), 15 (Sat) | Prius, Prius PHV, Corolla |
Production line #2 | October 8 (Sat), 15 (Sat) | ― | Corolla Sport, Camry, Crown | |
Toyota Motor Corporation Tahara Plant | Production line #1 | October 10 (Mon), 11 (Tue), 12 (Wed), 13 (Thu), 14 (Fri), 15 (Sat), 17 (Mon), 18 (Tue), 19 (Wed), 20 (Thu), 21 (Fri) | Land Cruiser Prado, Lexus GX, 4Runner | |
Production line #3 | October 6 (Thu), 7 (Fri), 8 (Sat), 14 (Fri), 15 (Sat) | ― | Lexus LS, IS, RC, RC F, NX | |
Toyota Motor Kyushu Miyata Plant | Production line #1 | October 8 (Sat), 15 (Sat) | Lexus NX, NX450h+, ES, CT, UX, UX300e | |
Production line #2 | October 10 (Mon), 11 (Tue), 12 (Wed), 13 (Thu), 14 (Fri), 15 (Sat), 17 (Mon), 18 (Tue), 19 (Wed), 20 (Thu), 21 (Fri) | Lexus ES, RX | ||
Toyota Auto Body Inabe Plant | Production line #1 | ― | October 15 (Sat) | Hiace, Granace, Alphard, Vellfire, Lexus LM |
Toyota Industries Corporation | Production line #301 | October 8 (Sat), 10 (Mon), 11 (Tue), 12 (Wed), 13 (Thu), 14 (Fri), 15 (Sat), 17 (Mon), 18 (Tue), 19 (Wed), 20 (Thu), 21 (Fri) | ― | RAV4 |
Production line #302 | RAV4, RAV4 PHV | |||
Hino Motors, Ltd. Hamura Plant | Production line #1 | October 6 (Thu), 7 (Fri), 14 (Fri), 21 (Fri), 28 (Fri) | October 10 (Mon), 11 (Tue), 12 (Wed), 13 (Thu), 17 (Mon), 18 (Tue), 19 (Wed), 20 (Thu) | Land Cruiser Prado, FJ Cruiser |