³Ô¹ÏÍøÕ¾s Member for Coffs Harbour, Gurmesh Singh, has provided an update on the Coffs Harbour Bypass project.
Mr Singh said blasting for the Gately’s Road tunnel has begun, and some minor traffic switches have occurred at the Korora end.
Earthworks are continuing with over 1.3 million cubic meters of dirt moved so far.
Over the next few months we will see:
- Shephards Lane and Bennetts Road realignments
- Preparing tunnel portals for Roberts Hill and Shephards Lane
- Start the bridge over the Railway Line
- Some of the work completed so far:
- 21 out of 34 culverts in place
- 108 out of 272 bridge piles in place
- 8 of 17 bridges under construction
You can download the latest project update here.
Community information session
A community information session on the bypass will be held next Tuesday, March 12.
It’ll be in the Marina Room at Pacific Bay Resort from 3:30 to 6pm.
Members of the project team will be available to answer your questions and share information on upcoming work. There’s no formal presentation, so feel free to drop in at any time.