³Ô¹ÏÍøÕ¾

Coomera Connector Stage 1 North construction reaches one year milestone

Minister for Transport and Main Roads and Minister for Digital Services The Honourable Bart Mellish

Coomera Connector Stage 1 North construction reaches one year milestone

  • The Coomera Connector Stage 1 North package will reach its one-year construction milestone next month.
  • Stage 1 of the Coomera Connector is 16 kilometres long and is being delivered in three construction packages: North, Central and South.
  • Stage 1 North is the four-kilometre section from Shipper Drive, Coomera to Helensvale Road, Helensvale, and is expected to open to traffic from late 2025.

Password: CC2024

Another milestone has been achieved for the Coomera Connector Stage 1 North package with the first year of construction nearly complete.

Since construction started for the North package just under 12 months ago, the project team has completed more than 80 per cent of piling works on both the new, nearly one-kilometre-long Coomera River bridge and Coomera overflow bridge, with 148 piles installed to date.

In that time, the project team has started bridge girder installation with 16 of close to 500 girders installed on the new Coomera River bridge.

Extensive ground improvement works are also underway, including the installation of close to 3,500 controlled modulus columns across the project, to stabilise and reinforce the ground.

Additionally, over two kilometres of new drainage infrastructure is now in place, with more than 2,000 workers inducted to the construction site.

Construction of the Coomera Link Road upgrade (Shipper Drive and Foxwell Road) is also underway.

/Public Release. View in full .