Orange City Council road crews will be busy on a number of projects this week.
Weather-permitting, the next step in the Council large-scale patching program starts this week.
Crews will be working on patching in the western end of March Street this week.
The work is funded by $967K from the NSW Government’s Regional & Local Roads Repair program.
Work also continues this week on the upgrade of Clergate Road.
Council’s water crews will start on the installation of a 450 mm water main in Clergate Road.
Crews will also be working on pot-hole pathcning in Forest Road.
Crews are making steady progress on the construction of a new roundabout at the corner of Dalton and Sampson Streets.