Upgrade to Bucketts Way at Clareval

MidCoast Council

Resurfacing of a section of the the Bucketts Way at Clareval will take place this week, weather permitting.

This stage of the project involves almost 1km section of road approximately 4km north of Stroud Road. Works will include widening of the road and drainage improvements.

With preliminary works complete, preparations began on Friday 24 March with the next project stage to kick off today, Monday 27 March. It will take approximately three months to complete.

Traffic control measures will be in place during all stages of the works. Single-lane traffic conditions may create minor delays.

These works on the Bucketts Way are funded by the Australian Government’s Roads of Strategic Importance initiative with contribution from the NSW Government. The Australian Government’s contribution is capped at $20 million, with the total project cost projected to be $25 million.